PROPOSITION C > PROJECT: FIRE STATION 271

1The project in Proposition C includes the construction of a new Fire Station and Emergency Operations Center (EOC) to replace the existing Fire Station on Camp Wisdom Road, as well as replace the existing Emergency Operations Center.
Rendering of Fire Station No. 1

Overall Project Status

Study100% Complete
Design100% Complete
Construction97% Complete

Project Details

Bond Program Year: 2018

Proposition: C

Project Name: Fire Station 271

Project Description: Construct a new Fire Station #1 to replace existing facility

Project Status: Land Acquisition Underway

Project MAPS: Projects Map

Last Modified Date: 01/23/2024

Project Schedule (subject to change)

Fall 2018 - Voters Approved Bond Election
Winter 2019
- Design Work Begins
Summer 2022
- Construction Contract Awarded
Fall 2022
- Construction Work Begins
March 2024 -Estimated Completion

Project Cost Breakdown (by %)

ESTIMATED PROJECT COST BREAKDOWN

Purchase of Land: $1M (9%)
Engineering & Design:  $750,000 (7%)
Construction, IT, and Furnishings:  $9.43M (84%)

$11,180,000

TOTAL COST