PROPOSITION B > PROJECT: DANIELDALE RD.

This project in Proposition B includes the reconstruction of pavement and subsurface utilities along a segment of Danieldale Road. The proposed configuration will be a four-lane divided roadway with hike and bike trails north and south of the roadway.

(Continued after image)

Danieldale Reconstruction

Overall Project Status

Danieldale Road
Study100% Complete
Design100% Complete
Construction97% Complete

Project Details

Bond Program Year: 2018
Proposition: B
Project Name: Danieldale Rd.
Project Description: Reconstruct street and subsurface utilities to include bike and pedestrian facilities along Danieldale Rd. between Main St. and US 67
Project Status: Construction Underway
Last Modified Date: 01/22/2024

Project Schedule (subject to change)

Estimated Design Start: Spring 2019
Estimated Design Completion: Spring 2020
Estimated Construction Schedule: March 2021 –Winter 2024
Estimated Construction Completion: Winter 2024

Project Cost Breakdown (by %)

ESTIMATED PROJECT COST BREAKDOWN

Engineering & Design: $651,000 ($324K Bond - 4%; $327K Utilities CIP - 4%)

Construction: $7,200,000 ($2.8M Bond - 36%; $4.4M Utilities CIP - 56%)

$7,850,000

TOTAL COST